Unpacking your fence assembly – SawStop Fence Assembly User Manual

Page 3

Advertising
background image

SawStop Contractor Fence Assembly 1

Unpacking Your Fence Assembly

fence

left rear rail

right rear rail

material

support shelf

front rail

Installing the Fence Rails Assembly

Hardware for Steps 1-11

Square Head Screws, M8 x 20

(10 + 1 extra)

16

Lock Washers, M8

(22 + 1 extra)

17

Hex Nuts, M8

(18 + 1 extra) 18

Hex Screws, M8 x 16

(8 + 1 extra)

19

Carriage Bolts,

M8 x 20 (4)

20

Hardware Pack

#

3

Sa

w

St

op

SawStop

®

OWNER’S MANUAL

Contractor Fence Assembly

owner’s manual

hardware pack #3

fence

handle

large

storage

hook

(two)

small

storage

hook

(two)

S

a

w

S

to

p

• Mount the left rear rail (the shorter rail)

to the rear of the table and to the left extension

wing using three M8 x 16 hex screws , three

M8 lock washers , and one M8 hex nut . Insert one hex

screw into the hole in the extension wing and then use a lock

washer and hex nut to hold the screw in place, as shown. The

other two hex screws thread into corresponding holes

in the cast iron table. Place a lock washer on each

screw before threading them into the holes. Hand

tighten the hex screws; do

not fully tighten them.

Installing Your SawStop Contractor Fence Assembly

6

5

4

7

3

8

2

Installing the Fence Rails

Assembly

• Locate the front rail, the left and right rear rails, and hardware

pack #3. All of the hardware needed to install the rails is located

on hardware pack #3. In order to easily identify the hardware

used in each of the following steps, the different pieces of

hardware are numbered on the hardware pack and in the figures.

If you are missing hardware pack #3 or any of the other fence

assembly components, call the SawStop Service Department at

503-682-6222 for replacements.

You will also need the following tools

to complete the fence assembly:

1. two 13 mm wrenches

2. a level or straight-edge

3. a rubber hammer or mallet

• Adjust the position of each square head screw so that all eight

screws align with the corresponding mounting holes in the front

edge of the table top and extension wings. Position the front rail

against the edge of the table with the eight screws

extending through their corresponding mounting holes.

Make sure the rulers on the front rail are facing up.

• Place an M8 lock washer and thread an M8 hex nut on

the back of each of the eight square head screws, but do

not fully

tighten the nuts at this time. Position the front rail so that the left

end of the rail extends about ⁄ inch past the edge of the left

extension wing.

17

18

• Use a straight-edge to level the rear edge of the left extension

wing to the cast iron table top. You may have to pull up or push

down on the outer edge of the extension wing to level it. Once the

rear edge of the left extension wing is level, use 13 mm

wrenches to fully tighten the hardware that mounts the

left rear rail. Repeat this process to level the rear edge

of the right extension wing and secure the right rear rail.

19

17

19

19

17

18

17

• Repeat the same procedure to mount the right rear rail (the

longer rail) to the rear of the table and to the right extension

wing. Again use three M8 x 16 hex screws , three M8 lock

washers , and one M8 hex nut . Hand tighten the hex

screws; do

not fully tighten them. The right rear rail should

extend beyond the right extension wing.

19

19

19

17

17

17

18

19

17

18

17

• Locate the material support shelf, the two large storage hooks,

the two small storage hooks, and hardware pack #3. All of the

hardware needed to assemble the material support shelf is

located on hardware pack #3. Take the material support shelf

and insert two M8 x 20 square head screws into the holes on

one end. Place an M8 lock washer and a M8 hex nut on

the back of each screw, but do

not tighten the nuts.

17

16

18

18

16

1

Installing the Fence Rails

Hardware for Steps 1-10

Square Head Screws, M8 x 20

(10 + 1 extra)

16

Lock Washers, M8

(22 + 1 extra)

17

Hex Nuts, M8

(18 + 1 extra) 18

Hex Screws, M8 x 16

(8 + 1 extra)

19

Carriage Bolts,

M8 x 20 (4)

20

Hardware Pack #3

Sa

w

St

op

16

16

Remove eight M8 x 20 square head screws from the

hardware pack and slide the square head of each screw into the

slot along the rear edge of the front rail.

16

18

17

3 4

19

18

17

straight-edge

Installing the Fence Rails

Hardware for Steps 1-10

Square Head Screws, M8 x 20

(10 + 1 extra)

16

Lock Washers, M8

(22 + 1 extra)

17

Hex Nuts, M8

(18 + 1 extra) 18

Hex Screws, M8 x 16

(8 + 1 extra)

19

Carriage Bolts,

M8 x 20 (4)

20

Hardware Pack #3

Sa

w

St

op

SawStop Service Department

503-682-6222

www.sawstop.com

© SawStop, LLC

installation instructions poster

®

While unpacking your fence assembly verify that all the components shown on this page are included. Use

care when unpacking your fence assembly to prevent damage to any of the components.

Advertising