ASSEMBLY & INSTALLATION


FILLING CANISTERS

After all of the canisters have been installed on the turntable, they can be
filled. Each canister has a maximum capacity of 2-1/2 quarts. It is
recommended that each canister be filled with two (2) quarts of colorant.
The maximum capacity of the pump is two (2) ounces.

The following steps represent the process by which the canisters should be
filled:

1. Locate the first canister and determine which colorant is to be placed

into that canister.

2. Place the appropriate decal on the canister.

3. Shake of stir the colorant following manufacturers recommendations.

4. Slowly, pour the colorant into the canister to the level of approximately

two (2) quarts.

5. Place the top on the canister.

6. Repeat these steps for each of the remaining canisters.

7. After all of the canisters have been filled, agitate by turning on the

agitation motor. This will release any air trapped in the colorant.

PRIMING OF PUMPS

Once the canisters have been both filled and agitated, the pumps attached to
each of the canisters must be properly primed. Follow these steps to prime
the pumps.

1. Locate the first canister.

2. Slowly pull the pump handle all of the way to the top of its stroke and

wait in this position for a count of approximately three (3) seconds.

3. Slowly press the pump handle all of the way down to the bottom of its

stroke.

4. Repeat these steps five (5) times.