Installation instruc tio ns – Poison Spyder TJ FULL CAGE KIT User Manual
Page 3

INSTALLATION INSTRUC
TIO
NS
Poison Spyder Customs • TJ FULL CAGE KIT INSTALL
Page 3
©2010 POISON SPYDER CUSTOMS, INC. • 951-849-5911 • WWW.POISONSPYDER.COM
FIGURE 3
4. Install the C-Pillar Mount Plates L&R
3
where the factory roll bar bolted in at the rear
corners. Orient the plates with the rounded
point edge facing the rear of the Jeep.
Secure them using the OE hardware.
FIGURE 4
5. Weld the gusset seam on each of the
Lower A-Pillars L&R
4
. This seam was left
un-welded so that you may weld it to match
the weld style of the rest of your cage. For
instance, if you are TIG welding your cage,
you would likely prefer to have your own TIG
weld in such a highly visible spot as this.
FIGURE 5
6. Install the Lower A-Pillars L&R
4
. Bolt
each Lower A-Pillar into place using the
three Torx bolts you removed during Step 5
of the Factory Cage Removal process. Note
that once installed, the Lower A-Pillars will
NOT be oriented perpendicular to the Jeep.
They will angle slightly inward. Be sure to
test-fit the doors for proper closing, before
proceeding.
4
9
8
2
3
10
15
13
12
11
16
14
6
7
1