9. Emergency Operation

■ Emergency Operation Procedures

The fol low ing pro ce dures are emer gency pro ce -
dures only.

DO NOT

use them for nor mal op er a -

tion. Their pur

pose is to get the plat

form and

op er a tor safely to ground when the MHP12/34J will
not start or some other prob lem keeps the plat form
from low er ing in the nor mal way.

❑

Operation From Platform Control Box

Switch set tings listed in the three steps be low must
ex ist at the ground be fore emer gency op er a tion
pro ce dures will work at the plat form con trol box:

Figure 9.1

1. The

Master Key Switch



must be ON (see

Figure 9.1).

2. The

Emergency

Stop

switch

€

must be

(ON) (see Figure 9.1).

3. The

Platform/Ground Selector

switch



(see Figure 9.1) must be set to PLATFORM.

Figure 9.2

4. Set the

Emergency Stop

switch

‚

to ON

(see Figure 9.2).

5. Set the

Anti-Restart

switch

ƒ

(see Figure

9.2) to ON.

Figure 9.3

6. Step on the platform foot switch

„

(see

Figure 9.3).

Figure 9.4

7. Hold the

Emergency Lower

switch

…

(see

Figure 9.4) down and the platform will begin
lowering.

NOTE

To slew when using emergency lowering operate
the slew switch
† in the direction required (see
Figure 9.4).