Sequencing cable adjustment, Sequencing cable adjustment -33, Mast side profile mast chain/cable adjusters – JLG 41AM (3120872) Service Manual User Manual

Page 55

Advertising
background image

SECTION 2 - SERVICE PROCEDURES

3120872

– JLG Lift –

2-33

one side or the other.
The threaded end of the chain/cable may need to be
restrained while tightening the adjust nut to keep the
chain/cable from twisting.

7. Retract the mast all the way and check if the top of

the mast sections appear as shown in Figure 2-6.

8. Repeat steps (1) through (7) for remaining mast sec-

tions.

9. Once mast section adjustment is completed, apply

loctite #242 to the threads under the (jam) nuts that
were loosened. Then re-tighten the loosened (jam)
nuts until tight against the top (adjust) nut. Chain/
cable should have slight tension but should not be
taut.

Sequencing Cable Adjustment

1. Retract mast completely, and check each sequenc-

ing cable on outside of masts for excessive slack.
Adjust only to remove slack from cable.

2. Tighten nylock-nut just enough to remove excessive

slack from sequencing cable. The springs should
not be compressed more than 25% after adjusting.

3. Run mast through several cycles to verify cable/

chain adjustments and ensure no interference exists
between chain anchor brackets and mast.

Figure 2-6. Mast Chain/Cable/Sequence Cable Adjustment Components. (Typical)

SECTION-1

FIXED

TO BASE

SEQUENCE CABLE

ADJUST NUT

CHECK IF OVERALL HEIGHT

OF MACHINE FROM

FLOOR TO TOP OF MAST

IS WITHIN SPECIFICATION

SECTION-2

EXTENDED BY

CYLINDER

SECTION-5

(PLATFORM

HEADER SECTION)

EXTENDED BY

CHAIN/CABLE

CHAIN/CABLE

ANCHOR PLATE

ADJUST NUT

JAM NUT

THREADED

CHAIN/CABLE

END

SECTION-4

EXTENDED BY
CHAIN/CABLE

SECTION-3

EXTENDED BY

CHAIN

STEP APPROXIMATELY

7/16 in. (11mm)

MAST SIDE PROFILE

MAST CHAIN/CABLE ADJUSTERS

Note:
When chain adjustment
is complete, before
tightening the jam nut

against the adjust nut,
apply Loctite #242 to the
threads under the jam nut.

Advertising