8. For Pit Mounted Lifts - the pit has been poured 1/2" – 3/4" deeper than the total

thickness of the carriage platform for shim and grout as required.

9. For Through-Floor or Shaft Installations – when clearances are tight, you may choose

to position the carriage after the beams have been assembled and raised into place.
For these installations, refer to Figure 18 to see how to properly lay out and locate
the beams prior to setting the carriage.


































Figure 18 Layout of Mast Foot Plates Prior to Setting Carriage

(When necessary for some Pit/Shaft installations)

INSTALLATION

INSTRUCTIONS

1/2 x CARRIAGE

LENGTH

+

1.0"

DETERMINED BY

INSTALLATION ANGLE

CENTER OF MAST BEAM WEB

PIT OR SHAFT

OPENING