65-2641RK-04 M2A Transmitter Operator’s Manual

Chapter 3: Installation & Startup

Overview

This chapter describes procedures to mount the M2A Transmitter in the monitoring
environment and wire it to input power and devices.

Mounting the M2A Transmitter

1.

Select a mounting site that is representative of the monitoring environment. Consider
the following when you select the mounting site.

For the M2A junction box, select a site where the junction box is not likely to be
bumped or disturbed. Make sure there is sufficient room to perform start-up,
maintenance, and calibration procedures. The site should be easily accessible.

For the detector junction box, select a site where the target gas is likely to be found
first. For lighter gases, mount the detector near the ceiling; for heavier gases,
mount the detector near the floor.

The junction boxes should be mounted no further than 200 feet from each other.

2.

Use #10 screws through the M2A junction box’s two mounting slots to secure the
junction box to a vertical surface. Figure 4 shows the outline and mounting
dimensions the M2A junction box. Figure 5 shows the outline and mounting
dimensions for the detector junction box. Mount the detector junction box with the
detector facing down as shown in Figure 5.

Figure 4: Outline & Mounting Dimensions, M2A Junction Box

.30 (2X)

3/4 NPT
Conduit Hub

5.23

.47 (2X)

2.41

5.00

1.02

5.86

4.59