INSTALLATION


The XT Flow Center is designed to work with larger heat pumps, single coil, dual stage heat pumps. To ensure adequate

flow the head loss of the geothermal piping system must be calculated and verified with performance curve (see Fig. 1).

The flow center must be located between the heat pump and the ground source system heat exchanger. Location should
be selected on the basis of ease of installation and future service. The flow center is used for filling, flushing, air

elimination, adding anti-freeze and operating the system. This flow center should never be pressurized.

The recommended piping schematic is usable with all types of closed-loop, ground source heat pump systems, vertical

bore holes, horizontal loops, slinky, outside headers or inside headers. This recommended method allows for isolating
the heat pump or the loop field for separate flushing and purging. Additionally, the flow through the loops can be

reversed, which may be required when using external headers.

NOTE: The XT Flow Centers are designed to work with only one heat pump per loop field. More than
one XT Flow Center on a common loop field will not work properly. Call B&D Mfg., Inc. for information

on equipment designed for multiple heat pumps.

Fig. 2 Illustrates a recommended piping schematic that can be utilized when an internal header is used and separate

purging of the heat pump and the ground loop is not required.

It is recommended that a tee with a threaded plug is located between the heat pump and the ground loop. This

plug allows the air to be vented from the system piping and will help remove air from the system during start up.

NOTE: Loops should not contain any dirt or debris prior to connecting to the flow center.

Fig. 3 Illustrates a recommended piping schematic for a system with underground headers.

Piping is similar for either schematic with the exception of Fig. 2 showing all earth loops penetrating the

mechanical area of the interior wall. Provide ball valves and P/T ports where indicated. Ball valves shall be same

as pipe size or greater. The flow center should be fastened to the wall with the bracket provided and all piping
should be adequately supported. All piping shall be properly sized for the flow rate (GPM) required by the system.

Reduce pipe size only at flow center and heat pump as necessary to make connections.

PROCEDURE 1—FILL AND FLUSH A NEW SYSTEM

On systems where the ground loop has been filled and flushed by the loop installer, skip to Procedure 3.

Ensure that all piping is installed according to one of the piping schematics.

NOTE: Incorrect piping may not eliminate the air pockets.

1. Open the top of the canister and fill with clean potable water.