PAGE 9 TP10243-1

ELECTRICAL CONNECTIONS

1.0 Wiring the Pump (2020 / 3 phase)

Connect the pressure/vacuum pump at the pump

junction box (Figure 5) using the attached cable. Follow the

instructions below for the proper connections.

There are six wires from the control box to the pump.

Wire #1 connects to the pump motor wires #1 & #7. Wire #2

connects to the pump motor wires #2 & #8. Wires #3

connects to the pump motor wires #3 & #9. Wires #4 & #5

connect seperately to the two pump motor wires marked

"THERMAL". Wire #6 is not used and should be taped off.

The remaining pump motor wires #4, #5, & #6 should be

connected together with a wire nut. The green wire is the

ground that is attached to the motor frame.

Turn the main power switch to the "ON" position.

Switch the pump on momentarily and check for proper

pump rotation as indicated by the rotation arrow on the

pump. Immediately turn off the pump if the rotation is

wrong.

If the rotation is incorrect interchange any two of the

three wires #1, #2, or #3 in the pump motor terminal box.

1.1 Wiring the Pump (2020 / 1 phase)

Connect the pressure/vacuum pump at the pump

junction box (Figure 5) using the attached cable. Follow the

instructions below for the proper connections.

There are six wires from the control box to the pump.

Wire #1 connects to the terminal marked 1 in the pump

motor. Wire #2 connects to the terminal marked 4 in the

pump motor. Wires #3 ,#4 ,#5 & #6 are not used and should

be taped off separately. The green wire is the ground that is

attached to the motor frame.

Figure 5

1.2 Other Connections

Refer to the serial number plate for electrical

requirements. The serial number plate notes the voltage,

phase and hertz, minimum time delay fuse, total machine

amperage, and minimum wire conductor size for the main

power connection.

The main power is connected directly to the line side of

the main power switch. In a 2020 single phase use L1 and

L2 only.

All electrical connections are to be made by a certified

electrician. Refer to local building electrical codes for proper

and safe connections.

For the following items, refer to Figure 6. Run a power

cable from your distribution box to the main control box on

the pile feeder. Turn the main power switch to zero. Using

the appropriate tool, open the latches on the control box

door and open the door.

NOTE: The door is connected to the main box by a ground

wire that should not be removed.