Installing the tpm – Bird Technologies 3140 Display User Manual

Page 14

Advertising
background image

Bird Electronics Corporation

4

Installing the TPM

The TPM has two RF connectors (Source and Load) that connect to the

transmission line, three test port connectors that are type N female

connectors (Forward, Reflected, and Test), and one nine-pin subminia-

ture communication connector (DB-9 Male).
1. Do the following:

•

Connect the RF connector labeled Source to the transmitter
side of the transmission line.

•

Connect the RF connector labeled Load to the antenna or load
side of the transmission line.

•

Use an appropriate coupling kit to secure the TPM in place.

2. Connect the DB-9 connector to a single channel on Model 3140A

power meter panel, or to an alternate appropriate power supply

and voltmeters that will indicate the forward and reflected power.

Note:

The chart below Figure 2 identifies the signals on

each pin of the DB-9 connector.

Note:

Above 4VDC, the accuracy spec does not apply.

CAUTION

Pin 4 must be connected to power supply ground,

other grounds can be left open if desired.

Pin

Description

1

Forward Voltage Output, 0 to 5 VDC, 1.0 kohm impedance

2

Ground

3

Reflected Voltage Output, 0 to 5 VDC, 1.0 kohm impedance

4

Power Supply Ground

5

DC Power Input, +11 to +18 VDC, <0.1 A current draw

6

Ground

7

Ground

8

Ground

9

Zero Calibration. DO NOT ground this pin. Leave this pin floating.

1

6

9

5

Pin 4 -

Power Supply
Ground

Figure 2

DB-9

Connector

Advertising