Vermont Castings VCBVTN/TP & VCPVTN/TP Room Heater

Pressure
Regulator

3/8” NPT Nipple

Tee Joint

Reducer
Bushing to
1/8” NPT

1/8” NPT
Plug Tab

Heater
Cabinet

Ground Joint
Union

Manual
Shutt-Off
Valve

From Gas
Meter

T

est Gauge

Connection

Tee Joint

Pipe Nipple

Cap

Sediment

T

rap

Natural Gas
(4” w.c. to
10.5” w.c. Pressure)
LP Gases
(11.5” w.c. to
14.0” w.c. Pressure)

RH103

Fig. 6 Gas line connection.

Open

Closed

Manual
Shut-Off
Valve

Manual
Shut-Off
Valve

Control Valve

RH104

Fig. 7 Manual shut-off valve location.

Leak Testing Heater Gas Connections

1. Open manual shut-off valve.

2. Open main gas valve located near gas meter.

3. Make sure control knob of heater is in the OFF

position.

4. Check all joints from manual gas valve up to control

valve and including the manifold assembly. Apply the
soap solution around the connections, valve and
tubing. Soap bubbles will appear where a leak is
present.

5. If a leak is present, immediately turn off gas supply,

tighten any leaky fittings, turn gas on and recheck.

6. To check burner and safety valve, the burner must

be lit (see Operating Instructions). Check the rest of
the connections for leaks.

7. Turn off the heater.

Pressure Test Gas Supply Piping System

The appliance and its individual shut-off valve must be
disconnected from the gas supply piping system during
any pressure testing of the system at test pressures in
excess of 1/2 psi.

The appliance must be isolated from the gas supply
piping system by closing the individual manual shut-off
valve (Fig. 7) during any pressure testing of the gas
supply system at test pressures equal to or less than
1/2 psi.