Machine leveling – Chief Manufacturing Pit Boss 638699 User Manual

Page 16

Advertising
background image

PIT BOSS

Users Manual

14

Machine Leveling


1. Position the PIT BOSS lift in the highest working position.

2. Use the scissor base as a template and a drill guide to install four (4)

concrete anchors (see Figure 27 & 28). See Anchoring section for more
information


3. Move around the machine placing a level across the front, rear, and down

both sides of the top. The machine should be level in all working heights.


4. Adjust level by adding the shims (see Figure 29). Repeat this process until

the machine is level on all corners.


5. Once the machine is level tighten the nuts on the concrete anchors. DO

NOT use an impact wrench for tightening


6. Depending on how many shims where placed under the PIT BOSS, shims

may need to be added to the Shop-Hopper. Shims for the Shop-Hopper are
placed between the caster and the frame.

Figure 29

Figure 27

Figure 28


Advertising