Ensure that the frame jamb is true and plumb. Anchor through the jamb and into the
condition as shown in figures 24 and 25 below. As a general guideline, anchors will be
located 2” from head and sill with a maximum of 16” O.C. and 1/2” shimming.
Remember these are general anchor location guidelines. The size, space, and
embedment of anchors required to meet structural loads per job specifications will override
these guidelines.