Figure #15, Step 3, Step 4 – EFCO WV410 User Manual

Page 14: Step 5, Step 6, Wv410 window - installation instructions

Advertising
background image

EFCO CORPORATION 2/2014 PART NO. Y007

Page

14

of

21

WV410 WINDOW - INSTALLATION INSTRUCTIONS

#

Section VIII – Window Installation

B. Dual Window Installation

Step 3

At the predetermined mullion locations, drill and tap the storefront horizontals for two (2) MRF7

10-24 PH-SMS fasteners. See Figure 15 below.

DETA IL G

DETA IL G

7/8 in [.874]

7/32 in [.224]
15/32 in [.467]

C/L of

Mullion

Interior of

Storefront

Detail G

Interior of

Storefront

K320

#9837

#1F10

Figure #15

#SPC6

#MRF7

Step 4

First apply sealant to the attachment hole in the storefront horizontals to insure against water

penetration, then install the K320 shear blocks using (2) MRF7 screws.

Step 5

Apply sealant to both ends of the female 1F10 and the male 9837 halves of the vertical mullion.

Step 6

Attach female portion 1F10 of the mullion to the shear block with (1) SFP6 screws at each end of
the mullion half. See Figure 15 above.

Shear block and all screws are
included in the K320 package.

(2) required per mullion.

* Drawings on this page are not to scale.

Advertising