Series 406x storefront installation instructions – EFCO 406X Series User Manual

Page 18

Advertising
background image

Series 406X Storefront Installation Instructions

EFCO 2014

Page 18

Section 4B. Sill Flashing Installation (cont.)

Splicing Steps:

1. Verify Sill Flashing - Check to see that sill flashing has been installed correctly. Sill flashing to be spliced every 20’

- 25’. Splice locations are to be located at least 6” from any vertical intermediate mullion.

2. Splice Gap - Make sure a 1/4” gap is left at every sill flashing splice location.
3. Splice Material -
Use a silicone type sealant and a strip of WM01 bond breaker tape. Tape is to be 1 7/8” wide by

approximately 7 1/2” long.

4. Apply silicone to both sides of sill flashing ends and fill 1/4” void between sill flashing ends as shown in Fig. #19.
5.
Center bond breaker tape splice over gap and set into sealant. Tool the sealant over the edges of the splice to

create a watertight seal.

6. Interior Gap - After the splice is installed, apply a cosmetic seal to the interior gap vertically up the splice. (Fig. #20)

Notes:

 These recommendations are for general erection procedures only.

 For actual job conditions, see the details on the shop drawings.

 Follow these splice guidelines at sill flashing corners also with one modification. No Gap.

Sealant

21V1 Sill Flashing

Sealant

Apply sealant to

interior gap.

21V1 Sill Flashing

Run sealant in 1/4” gap at

these two points.

Fill 1/4” void

between sill

flashings.

Bond Breaker Tape Splice

Fig. #19

Fig. #20

Advertising