STEP 9

install second unit by bringing into position from inside of building and interlocking back legs of

mullion (See Detail C, page 11).

Place appropriate shims beneath sill member to allow for better alignment, and rotate unit inot

place. Plumb and anchor.

Repeate Step 6 for all additional units. Miniumn 1/4” calulk joint at jamb is required for installation

of final unit.

Once all individual frames are secured to the opening, completely seal exterior perimeter with a

continuous bead of Vulkem 921 polyurethane sealant or equal.