Chapter 3 control panel operating procedures, 1 introduction, 2 control panel description – AERCO BMK 2.0 LN Natural Gas 2008 User Manual

Page 21: Control panel operating procedures

Advertising
background image

CONTROL PANEL OPERATING PROCEDURES

3-1

CHAPTER 3 CONTROL PANEL OPERATING PROCEDURES

3.1 INTRODUCTION

The information in this Chapter provides a guide
to the operation of the Benchmark 2.0 Low NOx
Boiler using the Control Panel mounted on the
front of the unit. It is imperative that the initial
startup of this unit be performed by factory
trained personnel. Operation prior to initial
startup by factory trained personnel will void the
equipment warranty. In addition, the following
WARNINGS and CAUTIONS must be observed
at all times.

1

2

3

4

5

6

7

8

9

10

11

12

CAUTION

All of the installation procedures in
Chapter 2 must be completed before
attempting to start the unit.

WARNING

ELECTRICAL VOLTAGES IN THIS
SYSTEM MAY INCLUDE 460, 208
AND 24 VOLTS AC. IT MUST BE
SERVICED ONLY BY FACTORY
CERTIFIED SERVICE TECHNICIANS

WARNING

DO NOT ATTEMPT TO DRY FIRE
THE BOILER. STARTING THE UNIT
WITHOUT A FULL WATER LEVEL
CAN SERIOUSLY DAMAGE THE
UNIT AND MAY RESULT IN INJURY
TO PERSONNEL OR PROPERTY
DAMAGE. THIS SITUATION WILL
VOID ANY WARRANTY.

Figure 3-1.

Control Panel Front View

3.2 CONTROL PANEL DESCRIPTION

The Benchmark 2.0 Control Panel shown in
Figure 3-1 contains all of the controls, indicators
and displays necessary to operate, adjust and
troubleshoot the Benchmark 2.0 Boiler. These
operating controls, indicators and displays are
listed and described in Table 3-1. Additional
information on these items are provided in the
individual operating procedures provided in this
Chapter.