VRLA

6. Install floor-mounting hardware (supplied by installer)

Locate the rack’s general position, considering boundary and aisle clearances.
Locate floor-mounting locations.
Mark the floor for drilling floor anchor holes using dimensions shown below.

Ref. Dim.
Narrow Rack

A

36.0”

Narrow Rack

B

12.5”

Both Racks

C

15/16” diam.

Wide Rack

A

42.0”

Wide Rack

B

12.5”


7. Secure end-support frames to floor finger tight.


Depending on the installation method, sway braces can be installed per step 8 before securing end support frames
to the floor.

8. Install 2 sway braces to 2 end support frames and braces to themselves at their centers

Mounting hardware starting at outer rack surface – finger tight

1.25” (x) 3/8” – 16 Hex Bolt
3/8” Flat Washer
(materials being joined together)
3/8” Flat Washer
3/8” Star Washer
3/8” – 16 Hex nut

9. Assemble rack tiers (LOWEST first), level rack and torque bolts


Adjust distance between rails to accommodate length of batteries to be installed.

Do NOT install batteries at this time.

After assembling:

a) Place one KYDEX insulating strip onto each battery support angle
b) Level and square all rack materials installed to this point using installer supplied shims
c) Torque all mounting hardware to 46 ft lbs. Torque floor anchors per manufacturer’s specification.

Mounting hardware starting at top of rack surface – finger tight

1.0” (x) 3/8” – 16 Hex Bolt
3/8” Flat Washer
(materials being joined together)
3/8” Flat Washer
3/8” Star Washer
3/8” – 16 Hex nut

Mounting

Hardware
Locations

End

Support

Frame

Rear View

Sway Brace

C

(Diam.)

(Insides facing)

A

B

Floor Mtg. Holes

End Support

Frames

Rails

Mounting

Hardware

Top View

End

Support

Frame