C&D Technologies RS-2109 Liberty MSE / Liberty DCS User Manual

Page 27

Advertising
background image


RS02109/0814/CD

27

www.cdtechno.com

Figure A12

Module Stacking/System Assembly
(Tiers 2 and higher)


1. Using either of the two lifting methods

described on the previous sheet continue
with stacking modules for tiers (2) on up.
As mentioned before it is always a good
practice to reference C&D connection
diagram while stacking modules to assure
proper cell orientation. Doing so can save
time and effort in the future if a module is
installed in the incorrect orientation.





2. Once the module is in position and bolt

holes are in alignment make the Module –
to – Module connection using (4) 10mm
bolts (2/side) in the horizontal plane.
Torque to 40 ft-lb [55 N*m].
(See Figure A14).






3. Follow these steps for any additional

modules for tiers 2 on up.



Note: Module – to – Module connection only
requires the use of (4) bolt connections per
tier in the horizontal plane (See Figure A14).

Figure A13

Figure A14

Advertising