Section 7

OPERATION

1.

Pre-operation checkoff:

Check the following before starting unit.

• Check that all wiring is correct.
• Check power supply voltage.
• Check that control power transformer terminals are connected to the correct

voltages.

• Check that there is no short-circuit.
• Check that terminal screws and connectors are tight.

2.

Pre-operation adjustments:

This inverter can be adjusted according to usage and load. Refer to section 5
(Adjustments) and make the proper adjustments.

3.

Operation procedure:

Refer to the standard connection diagram (Pages 14 and 15) and perform the

following: