4) It is strongly recommended that a Protective Post Pad be placed around the

gooseneck when the goals are in use.

FOOTING INSTALLATION

1) Excavate the footing hole to the appropriate dimensions as shown in Figure 2.

(See Figure 1 for locating the footing.) Pour the footing, using minimum 4,000
psi mix, to within 4” from ground level.

2) Assemble anchor rod to leveling plate by installing 7/8”-9 hex nut onto anchor

rod and engaging 7” of thread. Slip anchor rod thru holes in leveling plate
orienting the anchor rod as shown. Install second 7/8”-9 hex nut onto anchor rod
and tighten down so that the leveling plate is now held securely between the two
nuts. Place into concrete, level and square.

3) Let the foundation cure for a minimum of 48 hrs.

GOOSENECK INSTALLATION

1) Once the footing is complete and the concrete has set for 48 hours, rig the

gooseneck onto the anchor bolts, as shown in Figure 2.

2) Adjust the height and plum the gooseneck. Secure all hardware. Note: Due to the

weight of the crossbar and uprights the gooseneck will deflect downward 1” to 1-
1/2”.

3) All 7/8”-9 nuts and bolts should be coated with heavy grease. Each stud should

be protected by placing heavy poly film over greased studs and wrapping with
tape.


Cross-bar and Upright Installation



Crossbar Installation:

Use 10’ scaffolding and a ladder, have two people

on the scaffolding to lift and move the crossbar. Now with a third person on the ladder
guide the insert into the gooseneck.