Installing 24+2g gigabit ethernet web smart switch, 1 desktop installation, 2 rack-mount installation – Longshine LCS-GS8208-A V.1 User Manual

Page 8

Advertising
background image

2. Installing 24+2G Gigabit Ethernet Web Smart Switch

This switch can be placed directly on your desktop, or mounted in a rack. Users

can immediately use most of the features simply by attaching the cables and

turning the power on.

2.1 Desktop Installation

For desktop installation, the switch needs to put on a clean, flat desk or table

close to a power outlet. Plug in all network cables and the power cord, then the

system is ready.

Before installing the switch, you must ensure:

1.

It is accessible and cables can be connected easily

2.

Cabling is away from:

Sources of electrical noise such as radios, transmitters and broadband

amplifiers

Power lines and fluorescent lighting fixtures.

3.

Keep water or moisture off

4.

Airflow around the unit and through the vents in the side of the case is great

for heat radiation (company recommend that you provide a minimum of 25

mm clearance)

To prolong the operational life of your units:

1.

Never stack unit more than eight sets high if freestanding

2.

Do not place objects on top of any unit or stack

3.

Do not obstruct any vents at the sides of the case

2.2 Rack-mount Installation

The switch may standalone, or may be mounted in a standard 19-inch equipment

rack. Rack mounting produces an orderly installation when you have a number of

related network devices. The switch is supplied with rack mounting brackets and

screws. These are used for rack mounting the unit.

Rack Mounting the Switch in the 19-inch rack:

1.

Disconnect all cables from the switch before continuing.

2.

Place the unit the right way up on a hard, flat surface with the front facing

toward you.

3.

Locate a mounting bracket over the mounting holes on one side of the unit.

6

4.

Insert the screws and fully tighten with a suitable screwdriver.