12. Terminate additional pairs to rockers as

required.

13. Assure all rockers are in the down position

and close customer security cover.

CBM Wiring (Screw Terminal Connections)

1.

For binding post terminations, strip customer

wire ½ inch and terminate to the
corresponding Tip (green) and Ring (red)
screw terminals.

Figure 7

Central Office Signal Testing

Sealed CBM

1.

Open customer security cover.

2. Insert RJ-11 plug into customer test jack to

isolate telco and customer wiring.

3. Using an ohmmeter, insert test clips into test

ports as shown (See Figure 8).

4. If continuity is measured,

a “short” may exist in

the customer premise.

5. Wires are ok if meter shows a reading.

Figure 8

Screw Terminal Connections

1. Open customer security cover.

2. Insert RJ-11 plug into customer test jack to

isolate telco and customer wiring.

3. Using an ohmmeter, check for continuity

between the conductive heads of the tip
(green) and ring (red) screws.

4. If continuity is measured,

a “short” may exist in

the customer premise.

5. Wires are ok if meter shows a reading.

6. Close customer security cover and inform

customer.

Customer Telephone Wire Integrity

Testing

1. Open customer security cover.

2. Using a working telephone, insert the

telephone RJ-11 plug into the customer test
jack (See Figure 9).

3. Wait a few seconds, lift receiver, and listen for

tone.

4. If dial tone is not present, then contact central

office service provider.

5. If dial tone is present, then a problem exists in

the customer telephone wires.