ASSEMBLY

PRE LIGHTING

CHECK

COMMISSIONING

Fit the side panels and the hood onto the appliance.

Instructions for this are enclosed with the panel pack.

Replace any internal parts previously removed.

Before initial lighting check the following points:

1. The bottom grate bars must all be fitted and should move
freely and easily when the riddling mechanism is operated.

2. The plates round the sides and back of the grate must be

in position and sitting correctly.

3. The throat plate must be fitted in the roof of the

appliance.

On completion of the installation and after allowing time for
the fire cement and mortar to dry out, the fire should be lit
and checked to ensure that the smoke and fumes are taken
from the appliance up the chimney and emitted safely. Also

check all joints and seals.

On completion of the installation and commissioning please

leave the operating instructions with the customer and
advise on the use of the appliance.

Page 11

SLX20 9.03

150°

170

147

608

394

156

i/d

84

265

405

506

547

199

260

548

SLX20 Dimensions

(All dimensions are in mm)

Knock outs for optional boiler

either side