Installation

(for qualified installers only)

27

© Travis Industries

4090807

100-01193_003

Vent Clearances

IN THE ENCLOSURE (under 82")
Vertical or Horizontal Sections:
6" Clearance Above
3-1/2" Clearance To The Side
2" Clearance Below

Horizontal Penetrations
(through walls, etc.)
(thimble is required - sku 98900030)
4" Clearance Above
2" Clearance To The Side
2" Clearance Below

Vertical Penetrations
(through ceilings, roofs, etc.)
(firestop is required - sku 98900029)
1" Clearance To the Side

ABOVE THE ENCLOSURE (over 82")
Vertical Sections:
1" Clearance To the Side
Horizontal Sections:
4" Clearance Above
2" Clearance To The Side
2" Clearance Below

Vent Installation

•

Slide the vent sections together and turn 1/4 turn until the sections lock
in place.

•

Screws are not required to secure the vent. However, three screws may
be used to secure vent sections together if desired.

•

High temperature sealant is recommended at the appliance starter
section connection (use high-temperature silicone or Mill-Pac®).

•

If disassembly is required, at time of re-assembly check to see if the vent
creates a tight fit. If it does not, apply high temperature sealant to the
joints of the affected sections.

•

Horizontal sections require a 1/4" rise every 12" of travel

•

Horizontal sections require non-combustible support every three feet (e.g.: plumbing tape)