21 CB 1 Series Public Address Installation Instructions
1.0 FOUNDATION (see Anchor Bolt Installation Instructions)
2.0 SET THE UNIT
2.1
Screw one set of nuts and washers onto the anchor bolts – After the foundation has set,
screw one set of nuts followed by one set of washers onto the anchor bolts. Set the nuts so
the lowest washer is about 2½ inches above the concrete and at an even height. To accom-
plish this, use a small level and check from front to back, side to side and diagonally. These
nuts are NOT adjustable after the unit is in place. The bottom edge of the Code Blue unit will
be ½-inch above the concrete when installed.
MPORTANT: The leveling of the bottom nuts is crucial to the leveling of the unit. A small er-
ror in the adjustment of these will be magnified after installation.
MPORTANT: A ½-inch minimum air gap is required between the foundation and the unit.
Moisture problems may result if this condition is not complied with.
2.2
Set the Code Blue unit on the anchor bolts – Align the phone plate in the desired direc-
tion and lift the Code Blue unit over the anchor bolts. The unit may be lifted using the bracket
on the inside of the unit.
Note that the unit weighs approximately 390 pounds. Use appropriate lifting materials and
methods to avoid possible injury and/or damage.
2.3
Secure the Code Blue unit – Access the mounting studs through the door on the side
of the unit. Place the second washer then nut and then tighten the mounting nuts onto the
anchor bolts. This may be more convenient if a long socket, extension and universal joint is
used to tighten the hardware.
3.0 INSTALL THE DOME TOP ASSEMBLY
3.1 Remove the clear Lexan dome from the black metal casting. The casting, complete with
strobe, should be brought to the top of the unit where the wiring will be connected (match
black and red wire connectors; match yellow to yellow connectors).
3.2 After the wiring is complete, set the white disc on top of the lens located inside the unit (CB
1-d/1-s with Public Address only).
3.3 Set the casting on top of the unit and fasten the casting by reaching through the casting
openings and tightening the three 10-24 X 1-inch stainless steel thumbscrews against the
inner wall.
3.4 Finally, reattach the clear Lexan dome to the black metal casting with the security screws
provided.
NOTE: Take care not to overdrive the security screws against the Lexan as fracturing may
occur.
4.0 WIRING (refer to PAS WIRING DIAGRAM for additional details)
4.1 Ground – The ground (green) wire should be stripped and fastened to the supplied ground-
ing lug.
4.2 24V AC supply – Using the proper crimping tool, attach a #8 fork to each of the incoming
power wires and fasten them to the terminal screws labeled “Line” and “Neutral.”