Unvented natural gas log heater, Installation, Continued – Desa CCL3930NR User Manual

Page 12: Checking gas connections, Installing remote receiver unit

Advertising
background image

12

107553

UNVENTED NATURAL GAS LOG HEATER

For more information, visit www.desatech.com

INSTALLATION

Continued

Figure 14 - Equipment Shutoff Valve

ON

POSITION

OFF

POSITION

Open

Equipment
Shutoff Valve

Figure 15 - Checking Gas Joints

Gas Meter

Equipment
Shutoff Valve

Thermostat Gas
Valve or Control
Valve Location

Closed

WARNING: Never use an open

flame to check for a leak. Apply a
mixture of liquid soap and water
to all joints. Bubbles forming show
a leak. Correct all leaks at once.

WARNING: Test all gas pip-

ing and connections for leaks
after installing or servicing. Cor-
rect all leaks at once.

CHECKING GAS
CONNECTIONS

Pressure Testing gas Supply
Piping system

Test Pressures In Excess Of 1/2 PSIG
(3.5 kPa)

1.

Disconnect appliance with its appliance
main gas valve (control valve) and equip-
ment shutoff valve from gas supply pip-
ing system. Pressures in excess of 1/2
psig will damage heater regulator.

2.

Cap off open end of gas pipe where
equipment shutoff valve was connected.

3.

Pressurize supply piping system by either
using compressed air or opening main gas
valve located on or near gas meter.

4.

Check all joints of gas supply piping
system. Apply mixture of liquid soap
and water to gas joints. Bubbles form-
ing show a leak.

5.

Correct all leaks at once.

6.

Reconnect heater and equipment
shutoff valve to gas supply. Check re-
connected fittings for leaks.

Test Pressures Equal To or Less Than
1/2 PSIG (3.5 kPa)

1.

Close equipment shutoff valve (see Fig-
ure 14).

2.

Pressurize supply piping system by either
using compressed air or opening main gas
valve located on or near gas meter.

3.

Check all joints from gas meter to equip-
ment shutoff valve (see Figure 15). Ap-
ply mixture of liquid soap and water to
gas joints. Bubbles forming show a leak.

4.

Correct all leaks at once.

Pressure Testing Heater Gas
Connections

1.

Open equipment shutoff valve (see Fig-
ure 14).

2.

Open main gas valve located on or near
gas meter.

3.

Make sure control knob of heater is in
the OFF position.

4.

Check all joints from equipment shutoff
valve to control valve (see Figure 15).
Apply mixture of liquid soap and wa-
ter to gas joints. Bubbles forming show
a leak.

5.

Correct all leaks at once.

6.

Light heater (see Operating Heater,
pages 15 through 17). Check all other
internal joints for leaks.

7.

Turn off heater (see To Turn Off Gas to
Appliance
, page 16).

Front

Back

Front

Back

INSTALLING REMOTE
RECEIVER UNIT

1.

Disconnect switch wires from the con-
trol valve.

2.

Remove phillips head screws and heat
shield.

3.

Remove switch plate (see Figure 16).
Discard after removing.

4.

Install remote receiver unit onto gas log
heater base using phillips head screws.

5.

Connect wires as shown in Figure 18.

Figure 16 - Switch Plate and Wiring Har-
ness (Switch Plate and Orientation May
Vary Depending On Model)

Figure 17 - Installing Remote Receiver

Wires

Screws

Remote
Receiver

Screws

Figure 18 - Connecting Wires

Valve

White
Wire From
Receiver

Red Wire From Receiver