Assembly instructions akh3, Technical manual – Flowserve AKH3 Atomac Lined Ball Valve IOM User Manual

Page 6

Advertising
background image

AKH3 -

atomac ball valve - reduced port

Ahaus GmbH

von-Braun-Straße 19a

D-48683 Ahaus

Postfach 1162 D-48661 Ahaus

Telefon: +49(0) 2561-686-100

Fax: +49(0) 2561-686-200

Register:

3

Page:

6

Date:

05.1996

Revision: 08.2010

Technical Manual

DN8“ and 10“

Assembly Instructions AKH3

DN 1“ - 3“ = square flange

DN 4“ and 6“ = hexagonal flange

The general installation and maintenance instructions must be observed.

1. Screw stud bolts

(120) into body (010).

2. Insert stem

(040) from inside of body in such a way that the flat side is parallel to body longi-

tudinal axis.

3. Insert chevron packing

(100).

4. Install gland inersert

(065), gland follower (060), safety washers (150), hexagon nuts (110)

and grounding strap

(170) also on valves with actuator.

5. Install hand lever

(070) on to stem (040) and tighten it using lock washer (130) and hexagon

bolt

(140).

6. Insert first ball seat ring

(030) into body (010).

7. Insert ball

(050) to valve stem by pushing the ball in a downward motion through valve body.

8. Turn hand lever 90° of longitudinal axis of body.

9.

Install second ball seat ring

(030) on to ball (050).

10. Install side piece

(020) on to body (010), making sure that recess for stem is on the correct

side.

11. Install body bolts

(080) and hexagon nuts (090) and tighten by crisscross method to

recommended torques.

12. Assemble stop

(210) with hexagon bolt (220).

13. Make sure that the valve DN 10“ is in open position when it is installed into the piping

system.