Commissioning procedure, Operation – Flowserve NRG16-41 User Manual

Page 23

Advertising
background image

3

Apply power to switching controller NRS -4.

Commissioning Procedure

Make sure that the level electrode NRG ..-4 is properly connected to the switching controller

NRS -4 according to the wiring diagram,

Fig. 13.

Check wiring

Apply mains voltage

Operation

Used in combination with switching controller NRS -4 in (pressurized) hot-water plants and steam

boilers working in accordance with TRD 40, TRD 60, TRD 604 or other national regulations.

High-water level limiter (Max alarm)

Note

Should malfunctions occur during the commissioning procedure refer to section

“Troubleshooting” on page  in order to find, analyse and eliminate the fault.

Advertising
This manual is related to the following products: