0

. Take care of correct position of installation.
2. Take care of flow direction. The flow arrow is on the trap body.
3. Consider space required for opening trap. When the trap is installed a minimum space of

80 mm is

required for removing cover

A.

4. Remove plastic plugs. They are only used as transit protection.
5. Clean seating surfaces of both flanges.
6. Install steam trap.

Flanged design

. Take care of correct position of installation.
2. Take care of flow direction. The flow arrow is on the trap body.
3. Consider space required for opening trap. When the trap is installed a minimum space of

80 mm is

required for removing the cover

A.

4. Remove plastic plugs. They are only used as transit protection.
5. Remove regulator as described under

Maintenance.

6. Clean socket-weld ends.
7. Arc-weld trap (welding process  and 4 in accordance with ISO 4063).

Socket-weld design

Installation

Provided that the flow arrow (the arrow points towards the direction of flow) is taken into consideration,

the trap can be installed in any position. In the case of a horizontal installation make sure that the cover

is on top.