Installation

– continued –

Attention

n

Only qualified welders certified e. g. according to DIN EN 287 may weld the steam trap

into pressurized lines.

n

Do

not insulate the steam trap.

After welding the steam trap in place a heat treatment of the welds is required (stress-relief annealing

to DIN EN 00529). The heat treatment must be restricted to the immediate area of the welds. Remove

the regulator as described under

Maintenance before carrying out the heat treatment.

Heat Treatment of Welds

. Take care of correct position of installation.
2. Take care of flow direction. The flow arrow is on the trap body.
3. Consider space required for opening trap. When the trap is installed a minimum space of

80 mm is

required for removing the cover

A.

4. Remove plastic plugs. They are only used as transit protection.
5. Clean butt-weld ends.
6. Arc-weld trap (welding process  and 4 in accordance with ISO 4063) or use gas-welding

process (welding process 3 in accordance with ISO 4063).

Butt-weld design

n

Spanner A.F. 24 mm, DIN 33, form B