Switch on mains supply. The green LED is illuminated. Fig. 4

NRS 2-5 c/d

1. After switching on the mains voltage the green LED must be permanently

illuminated. Fig. 4

2. Lower the water level until it falls below the low-level mark.

The red LED at the level switch must light up.

3. Raise the water level until it exceeds the low-level mark. The red LED must

extinguish.

4. After removing the terminal box from the level electrode the yellow LED must

light up (malfunction in connecting wire).

5. Bridge terminals C16 and C18. The yellow LED must light up (malfunction in

electrode).

The measuring voltages of the different operating modes are represented in table 1.

Commissioning

Check whether the NRS 2-5 and the associated system component NRG 211 are
wired according to the wiring diagram. Fig.1, Fig. 2

Check wiring

Apply mains voltage

Functional test

Table 1

Measuring voltage U

M

Decoded

1 V

Malfunction in electrode supply cable
(short circuit, interruption)

1 V – 4 V

Electrode exposed, low level

4 V – 7 V

Electrode submerged

9 V

Malfunction in electrode (defective insulating seal,
leaking stuffing box)

4

4

3

1

2

Advertising