Installation

– continued –

Steam trap with socket-weld ends

. Observe position of installation.
. Observe flow direction. The flow direction arrow is located on the valve body.
. Leave at least

40 mm free space around the equipment for subsequent disassembly of the

cover

E.

4. Remove plastic plugs. They are

only used for transit protection.

5. Remove regulator as described in section

Maintenance.

6. Clean socket-weld ends.
7. Apply

only electric arc welding process (welding process  and 4 in accordance with

ISO 406).

Steam trap with butt-weld ends

. Observe position of installation.
. Observe flow direction. The flow direction arrow is located on the valve body.
. Leave at least

40 mm free space around the equipment for subsequent disassembly of the

cover

E.

4. Remove plastic plugs. They are

only used for transit protection.

5. Remove regulator as described in section

Maintenance.

6. Clean butt-weld ends.
7. Apply electric arc welding process (welding process  and 4 in accordance with

ISO 406) or gas welding (welding process  in accordance to ISO 406).

Attention

Only qualified welders certified e. g. according to EN 87- may weld the valve into

pressurized lines.

The valve must

not be insulated.

Heat treatment of welds

A subsequent heat treatment of the welds is not required.