Installation instructions for qualified personnel

Important points prior to in-
stallation

■

Transport the unit in its original
packaging as close as possible
to the installation location to
avoid transport damage.

■

Check the contents of the

packaging for completeness
and check the unit for visible
transport damage. Report any
damage immediately to your
contracting party and the ship-
ping company.

■

Lift the unit at the corners and
not by the refrigerant or con-
densation connections.

■

The refrigerant pipes
(injection and suction pipe),
valves and connections must be
insulated impervious to vapour
diffusion. If necessary, also insu-
late the condensation pipe.

■

Select an installation location
which allows air to freely flow
through the inlet and outlet.
(See section "Minimum clear-
ances").

■

Do not install the unit in the
immediate vicinity of devices
with intensive thermal radia-
tion. Installation near sources of
thermal radiation reduces the
output of the unit.

■

Open the blocking valves of the
refrigerant pipes only after the
installation is complete.

■

Seal off open refrigerant pipes
with suitable caps or adhesive
strips to avoid infiltration of
moisture
and never kink or compress the
refrigerant pipes.

■

Avoid unnecessary
bends. This minimises the pres-
sure loss in the refrigerant pipes

and ensures that the compres-
sor oil can flow back without
obstruction.

■

Use four supports and the as-
sociated hooks to attach the
ceiling cassette.

■

Use the insulated condensation
hose in the scope of delivery as
a junction piece to the continu-
ing condensate drain. Secure
the condensate drain with the
supplied clamps.

4 Fixing materials for RVD 261-681 DC

Suspension

Adapter piece

Insulation

Clamps