5

Insert the conduit through the wiring access entry and attach the conduit fitting to the panel.
Strip 0.5” (1.5 cm) of insulation from the end of each incoming wire.

6

Connect the input and ground wires to the terminal block according to Figure 21 and Table 1.

Figure 21. UPS Input Terminal Block

Table 1. UPS Wiring Specifications

Wire

Function

Terminal

Position

UPS Wire Function

Terminal Wire

Size Rating*

Tightening

Torque

Input

1

Input Ground

5.26–16 mm

2

(10–6 AWG)

2.26 Nm (20 lb in)

2

L2/Neutral In

3

L1 In

* Use 5.26 mm

2

(10 AWG) 75

_C copper wire minimum.

7

Replace the terminal block cover.

8

Continue to the following section, “UPS Initial Startup.”

UPS Initial Startup

To start up the UPS:

1

Verify that the internal batteries are connected.

2

If an optional EBM is installed, verify that the EBM is connected to the UPS.

3

Verify that all load segment circuit breakers are in the ON position.