3.4 Pump Installation
1. The well should be clean and disinfected before the pump is installed. You should always clean and
develop a new well before installing the pump.
2. Write the pump, motor and controller model number and serial number in the space provided on the last
page in this Instruction Manual. This information will be needed when filling out the Warranty Card. And
will aide in any troubleshooting which may be necessary.
3. Inspect all components for shipping damage and insure that you have all the components that are required
for a complete installation.
4. Select a well-ventilated, shaded location in which to vertically mount the control box. The shaded side of
the solar panel rack mounting pole is usually a convenient place.
5. If using unthreaded discharge pipe install a stainless steel or brass adapter fitting into the pump discharge
head. Consult your pump supplier for other available adapter materials. Do not use galvanized
connections on stainless steel or bronze discharge heads as galvanic corrosion will occur. Connect the
drop pipe, safety rope and sand shroud (if used) to the pump. Barbed type connectors should always be
double clamped. For poly pipe, compression fittings are recommended.
6. Splice the drop cable to the motor lead using an under water splice kit. (See wire splicing instructions
provided with splice kit.) Match the drop cable wire colors to the pump motor leads. If the drop cable does
not have the same color wires as the pump, be sure to record which colors go to the various colors of the
motor lead and label them. The motor can run in reverse if not connected properly.
7. You can now lower the pump into the well. Set the pump at least 10’ off the bottom (see 3.2 System
Design Basics #4). Never rest the pump on the bottom of the well. Never lower the pump by the
submersible pump cable.
8. Tie the drop pipe, drop cable and safety rope together every ten feet with 2” 10 mil pvc pipe wrap tape.
Make sure that the tape does not loosen as it will block the pump suction if it falls down the well. The use
of the safety rope is at the discretion of the installer.
9. Slide the well seal over the discharge end of the pipe, connect the discharge fitting, pull the drop wire
through the well seal and connect the safety rope, if used, to the eye-bolt on the inside of the well seal.
10. Finish lowering the pump and pipe assembly into the well (bore hole) positioning the well seal over the top
of the casing. Connect the discharge pipe to the fitting on top of the well seal and run the pump wires to the
controller.
3.5 Wiring
Prior to connecting any wires to the controller, be sure you have a system wiring diagram to use as a reference
(see figure 2). Guessing at polarity and connection points is not worth the risk of potential product damage
and/or personal injury.
Ensure the wire sizes are of adequate diameter (gauge) to minimize voltage drop. Please refer to a DC voltage
loss table or call your SunPumps dealer for assistance. Wire gauge being too small will cause excessive voltage
losses to the motor and will reduce the flow rate of the pump.
All other system equipment should be installed before proceeding with wiring the controller. Double check
polarity and wire termination tightness before powering up the system.
CAUTION: Photovoltaic panels produce DC electricity when exposed to sunlight. Cover the panels with
a blanket or with a non-opaque material before wiring. Install a disconnect switch between the solar
modules and the controller.
- MTR BLM-SB-203S-180 MTR BLM-SB-303S-240 PCC-120BLS-M2 PCC-180BLS-M2 PCC-240BLS-M2 MTR-BLM-SF-153C-120 MTR-BLM-SF-153C-90Y MTR-BLM-SF-303C-180 MTR-BLM-SF-353C-240 MTR-BLM-SF-153J-120 MTR-BLM-SF-153J-90Y MTR-BLM-SF-303J-180 MTR-BLM-SF-353J-240 SCP 100-60-180 BV SCP 115-60-240 BV SCP 50-50-120 BC SCP 58-51-48 BC SCP 62-42-105 BC SCP 67-50-120 BC SCP 75-40-105 BC SCP 80-55-180 BC SCP 86-55-180 BV SCP 86-65-180 BC SCP 94-37-120 BV SJT05-90BT SIJ 0.55-900P-90 BT SIJ 2.3-750P-150 BT SIJ 2.6-450P-90 BT SIJ 3.28-260P-75 BT SIJ 0.67-1500P-120 BL SIJ 2.2-1000P-105 BL SIJ 3.4-160P-45 BL SIJ 2.2-1300P-135 BL SIJ 2.9-700P-105 BL SIJ 3-640P-135 BL SIJ 3.1-220P-60 BL SIJ 3.1-700P-120 BL SJT10-120BL SCB-10-150-120 BL SCB-10-150-180 BL SCB-10-200-180 BL SCB-10-220-180 BL SCB-10-265-180 BL SCB-21-350-240 BL SCB-22-165-120 BL SCB-22-185-180 BL SCB-22-250-180 BL SCB-22-95-120 BL SCS 10-210-120Y BL SCS 10-440-180 BL SCS 12-127-60 BL SCS 12-160-120Y BL SCS 12-265-120 BL SCS 12-375-180 BL SCS 125-32-120 BL SCS 130-32-180 BL SCS 14-370-240 BL SCS 142-32-180 BL SCS 150-37-240 BL SCS 17-280-180 BL SCS 18-105-120Y BL SCS 20-180-120 BL SCS 20-190-180 BL SCS 20-90-120Y BL SCS 20-350-240 BL SCS 22-300-240 BL SCS 26-80-120Y BL SCS 30-130-120 BL SCS 30-165-180 BL SCS 30-240-240 BL SCS 44-80-120 BL SCS 45-116-180 BL SCS 50-110-240 BL SCS 7.5-250-120Y BL SCS 71-70-180 BL SCS 8-410-120 BL SCS 8-500-180 BL SCS 80-70-240 BL SCS 87-70-240 BL