6651-2201

Start up guide

Follow the steps below to get the unit up and running in a simple application.

… Use the factory DIP-switch settings.
… Connect The fibre link between the both units.
… Connect the power supply to both units.

The Fibre link should be in operation as indicated by the CH1 LED.

… Connect the PROFIBUS DP connectors between both ODW-710-F1 and PROFIBUS

units configured to be units in the PROFIBUS DP network.
The PROFIBUS DP will be in operation and the data rate will be automatically detect-
ed, as indicated by the BA LED.

… The point to point application is up and running.

Note: In an ODW-710-F1 fibre optic link there will be some additional processing

delays that do not exist in an electrical bus. It is possible that the PROFIBUS
application must be adjusted to accommodate for this delay. See page 21
“Calculating system processing delay” for more information on how to
determine the overall system delay time.

POWER

CH 1

COM +VA +VB COM

POWER

CH 1

COM +VA +VB COM

TX

RX

TX

RX

PROFIBUS DP master

Fibre Optic

PROFIBUS DP

PROFIBUS DP

PROFIBUS DP slave

Advertising
This manual is related to the following products: