INSTALLATION

Your LD9000 family of pole displays has been pre-assembled to make the
installation as simple as possible.


1. Mount the pole display to the metal base plate using the mounting

hardware provided.

2. The pole display can be used in a freestanding mode or attached to the

counter using the remaining mounting hardware.

3. Connect the round DIN6M connector from the pole display to the round

DIN6F connector of the interface cable.

4. Connect the DB9F connector to the computer’s serial COM1 or COM2

port.

5. Connect the female phone jack of the power adapter to the male phone

jack of the interface cable.

6. Plug the power adapter into a 120VAC outlet.
7. A start up text message (LOGIC CONTROLS POS COMPONENTS) will

be present for a short time. When this message disappears the cursor
will be displayed at the left-most digit of the top row.



Serial Interface Connector Pinout

1.

DCD (tied to pins 4&6)

2. NC
3.

RXD from PC

4.

DTR (tied to pins 1&6)

5. Ground
6.

DSR (tied to pins 1&4)

7.

RTS (tied to pin 8)

8.

CTS (tied to pin 7)

9. NC




FUNCTIONAL TEST


The following test sequence will verify that your pole display is working
properly. Before you start this procedure, you must install the pole display
correctly as outlined under the INSTALLATION section. The functional test
should be done under MSDOS command prompt by booting up the
computer in DOS mode, or shell out to DOS prompt (in Window95/98/ME) or
COMMAND prompt (in Windows NT/2000).

NOTE: The actual key entries in the text below are enclosed within

quotation marks ( “ ” ). Do not type the quotation marks as part of
your entries.


This test procedure assumes the pole display is connected to COM1 of the
computer. If COM2 is being used, type COM2 where COM1 is called out.

Close all opened application programs that use the same COM port before
shelling out to DOS COMMAND prompt. Enter the following command lines
to open the COM port for communication with the pole display:

Type “MODE COM1 96,N,8,1” and press the ENTER key.

Type “TYPE CON>COM1” and press the ENTER key.


LD9000, LD9300, LD9400, LD9500, LD9900


1. Type “ABCDEFGH” and press ENTER key. The display will show

“ABCDEFGH” on the first line.

2. To end the test press Ctrl-C (hold down Ctrl and press C).

LD9200

1. Type “!#1ABCDEFGH” and press ENTER key. The display will show

“ABCDEFGH” on the first line.

2. To end the test press Ctrl-C (hold down Ctrl and press C).

DB9F (to computer)