If the purge gas is heavier than air (such as argon), locate the inlet lower than the
outlet, so that the purge gas will displace air from bottom to top.

If the purge gas is lighter than air (such as nitrogen), locate the inlet higher than
the outlet, so that the purge gas will displace air from top to bottom.

5.

Make sure that there is a tight seal between the inlet connection and sensor case, so
that air cannot be drawn by suction into the case or purge line during the purging
process.

6.

Run purge gas through the sensor.

The purge time is the amount of time required for full exchange of atmosphere to
inert gas. The larger the line size, the greater amount of time is required to purge
the case. See

Table 5-1

. If purge lines are being used, increase the purge time to fill

the additional volume of the purge line.

Note

Keep the purge gas pressure below 30 psig (2 bar).

Purge time

Table 5-1:

Sensor model

Purge rate, in ft

3

/hr (l/h)

Time, in minutes

T025

20 (566)

1

T050

20 (566)

1

T075

20 (566)

3

T100

20 (566)

5

T150

20 (566)

10

7.

At the appropriate time, shut off the gas supply, then immediately seal the purge
outlet and inlet connections with the purge plugs.

Note

Avoid pressurizing the sensor case. If pressure inside the case elevates above atmospheric
pressure during operation, the flowmeter density calibration will be inaccurate.

8.

Make sure that the purge fitting seals are tight so that air cannot be drawn by
suction into the sensor case.

Supplementary information