7-INSTALLATION AND ASSEMBLY

SETTING UP THE CLADDING

All product functionalities must be tested before being clad. The company cannot be held liable for any damage to the

cladding should operating anomalies arise, which were not ascertained before the cladding was applied to the product.

IT IS OBLIGATORY to check seal of all piping the smoke goes through (smoke fitting, gaskets and insert in the flue) before

installing the cladding.

READ THE “OPERATION TEST” CHAPTER BEFORE STARTING ANY PRODUCT CLADDING OPERATION.

The product and parts of the cladding must be fastened to each other WITHOUT COMING IN CONTACT WIT THE STEEL STRUCTURE to

avoid transmitting heat to the marble and/or stone and to allow for normal thermal dilation; pay attention to wood finishes like beams

or shelves.

It is recommended to construct the counter-hood in fire-retardant plasterboard, 15 to 20 mm thick with self-supported galvanized profile

frame in order not to bear on the cladding components (wooden beams or marble architraves) which do not have a load bearing structure

and to be able to operate easily in the event of faults and/or future maintenance. Dry-assemble the hearth of the cladding

leaving a 1 cm gap between insert and hearth to perform insulation.

WOODEN BEAM INSULATION

If you wish to mount a wooden beam, it must be protected with adequate insulation from hot parts in order to prevent the risk of fire or

damage to the cladding.

INSTALLATION OF STANDARD CLADDING

The use and installation manual found in each specific cladding must be referred to for setting up product specific claddings.

FIGURE 8 - BEAM INSULATION

1.

APPLIED INSULATING AGENT OR TO BE

APPLIED

2.

WOODEN BEAM

3.

MARBLE OR OTHER MATERIAL