3.5. PHASE 3 – WALL FOR RECESSED INSTALLATION

Prepare the wall for recessed installation using fireproof material, such as fireproof plasterboard, and at least 3

steel uprights. For greater safety, you can use 6 uprights, inserted two by two). Provide an opening of 1060X570

mm, 160 mm from the floor (see drawing). The steel uprights must be placed vertically in the positions shown

(see drawing).

57

0

16

0

1060

MONTANTE ACCIAIO

MONTANTE

ACCIAIO

FILO FORO

90

CENTRO

MONTANTE

290

CENTRO

MONTANTE