Installation procedures, Outdoor unit installation, Connecting the piping – haier AC142ACERA User Manual

Page 15

Advertising
background image

Installation Procedures

Select whether the drain hose will be connected to

the left or right side.(Fig.3)

Insert the drain hose into the drain pan, then secure

the drain hose with a nylon fastener.(Fig.6)

Wrap the insulation (drain hose)around the drain

hose connection.(Fig.7)

Be sure to arrange the drain hose correctly so that

it is leveled lower than the drain hose connecting

port of the indoor unit.(Fig.18)

5. INSTALL THE DRAIN HOSE

Fig. 19

Fig. 18

NO

OK

Remove the hole cover.

Arrange the drain hose
lower than this portion

Drain hose

Piping hole

Base (Bottom)

Intake grill

VT wire hole

Pass the drain hose through here

Cut the grill

VT wire

Drain hose

CONNECTING THE PIPING

OUTDOOR UNIT INSTALLATION

1. FLARE PROCESSING

(1) Cut the connection pipe with pipe cutters so
that the pipe is not deformed.

(2) Holding the pipe downward so that cuttings
cannot enter the pipe, remove the burrs.

(3) Remove the flare nut from the indoor unit pipe

and outdoor unit and assemble as shown in

(Table1) and insert the flare nut onto the pipe,

and flare with a flaring tool.

(4) Check if the flared part "L" (Fig.20)is spread
uniformly and that there are no cracks.

Table 1

Pipe

Flare nut

Small pipe

Large pipe

Small (width across flats 22mm)

Large (width across flats 24mm)

2. BENDING PIPES

Fig. 21

The pipes are shaped by your hands. Be careful
not to collapse them.

Fig. 20

OK

NO

Extend the pipe by unwinding it

13

Liquid pipe

Diameter of pipe

Dimension A (mm)

1.0~1.2

6.35mm (1/4”)

Gas pipe

1.4~2.2

AC142ACERA
AC182ACERA

AC242ACERA

12.7mm (1/2”)

9.52mm (3/8”)

15.88mm (5/8”)

Liquid pipe

Gas pipe

L

Width across flats

L dimension

Advertising