G0524 Rip Saw

To remove the saw base unit from the crate

pallet:

1. Cut off and remove all plastic straps from the

crate.

2. Using a forklift, position the saw over the final

location.

3. Place the cast iron feet under the leveling

screws.

4. Lower the saw onto the cast iron feet as

shown in

Figure 13.

Figure 13. Cast iron feet.

5. Adjust the leveling screws until the saw table

is level.

The Model G0524 is a

heavy machine that

weighs approximately

1980 lbs. Serious per-

sonal injury may occur

if safe moving methods

are not followed. Use

the assistance of power

equipment when moving

the crate and placing the

machine.

Cast Iron Foot

(1 of 4)

Leveling Screw

(1 of 4)

Placement

To connect the power cord to the saw:

1. Read through Section 3: Circuit Requirements

to double-check that your setup follows the
safety and circuit requirements, and that
the power cord you use meets the minimum
requirements for this machine.

2. Open the electrical panel box.

3. Feed the power cord through the strain

relief on the side of the electrical panel, and
connect the cord wires to the main terminal
(

Figure 14).

Figure 14. Main terminal located inside saw

electrical panel.

4. Close the electrical panel door.

5. DO NOT connect the power cord to the

power source at this time.