Attach free end (large
tag M10) to Tower Metal
work – NB On no ac-
count must this be at-
tached to the mount-
ing bracket bolts!!

Step 1: Your equipment will already have the
mounting bracket fitted.




Do not
remove pre-fitted mounting
bracket.

The pre-fitted earth bonding lead is secured
after the unit is mounted.


Step 2: Attach the Bracket mount to the pole
using the bracket strap and either M8
x 40mm or M8 x 70mm bolts, as required, M8
flat washers and M8 coil washers as shown.
Tighten to ensure the assembly grips but
can be adjusted. For poles between
1” (26mm) and 2”(50mm) reverse the
bracket.




Step 3: Offer up the unit to the bracket
mount and affix using the captive M8 bolt.
Tighten to ensure the assembly grips but can
be adjusted on the pole.


Step 4: Adjust the elevation and azimuth of
the unit before tightening to the required
torque settings of 14Nm
(11lbft) for both bolts.

Warning ! Do not over tighten.