9-3. Correct Installation

1

High-Frequency Source (welding power

source with built-in HF or separate HF

unit)

Ground metal machine case, work output

terminal, line disconnect device, input supply,

and worktable.
2

Center Point of Welding Zone

Midpoint between high-frequency source and

welding torch.
3

Welding Zone

A circle 50 ft (15 m) from center point in all

directions.
4

Weld Output Cables

Keep cables short and close together.

5

Conduit Joint Bonding and Grounding

Electrically join (bond) all conduit sections

using copper straps or braided wire. Ground

conduit every 50 ft (15 m).
6

Water Pipes and Fixtures

Ground water pipes every 50 ft (15 m).
7

External Power or Telephone Lines

Locate high-frequency source at least 50 ft

(15 m) away from power and phone lines.
8

Grounding Rod

Consult the National Electrical Code for spec-

ifications.

Metal Building Requirements
9

Metal Building Panel Bonding Methods

Bolt or weld building panels together, install

copper straps or braided wire across seams,

and ground frame.
10 Windows and Doorways
Cover all windows and doorways with

grounded copper screen of not more than 1/4

in (6.4 mm) mesh.
11 Overhead Door Track
Ground the track.

Ref. S-0695 / Ref. S-0695

1

2

3

50 ft

(15 m)

Weld Zone

4

7

50 ft

(15 m)

8

5

8

6

Ground

workpiece

if required

by codes.

Ground all metal ob-

jects and all wiring in

welding zone using

#12 AWG wire.

Nonmetal