note: if this required 10 foot (3 m) distance to a parapet,

vertical wall or structure cannot be maintained, standard

terminations must be used. See Vertical Termination

installation on page 27.

5. When installing a concentric termination through a sidewall;

ensure that all exterior sidewall clearance requirements for

the termination, shown in Figure 49 on page 37, are being

maintained. These clearances and those cited by local and

national codes must be maintained.

6. When installing multiple concentric terminations vertically

through a roof or horizontally through a sidewall ensure the

required clearances between terminations and groupings of

multiple terminations are maintained. See pages 32 and

33 for more information.

7. Cut a 5 inch (13 cm) diameter hole for the 4 inch concentric

termination where the termination will pass through the wall or roof.
note: beware of concealed wiring and piping when cutting

through the wall or roof.

8. When installing multiple concentric terminations vertically

through the roof in the same location the termination caps

for all concentric terminations must be at the same height

measured from ground. See multiple Concentric Termination

Arrangements on page 33.

9. Determine if the concentric termination will need to be

shortened or lengthened to accommodate required clearances

or to ensure all vent caps are at the same height when

installing multiple terminations vertically through the roof in the

same location.
See Figure 29 on page 31 for the maximum and minimum

lengths allowed for the 4 inch concentric termination.
When extending the length of a concentric termination

do not use couplings. The use of couplings will restrict

flow through the termination and may cause improper

combustion. The termination’s intake air and vent pipes must

be replaced with longer sections of the same pipe material

when extending the length of the termination.
Use only SDr-26 pipe to extend the 4 inch concentric

termination.
When shortening the length of the termination carefully

measure and cut the larger (intake air) pipe first. Cut the

same amount of pipe off of the smaller (vent) pipe.

10. Proceed to 4 inch Concentric Termination installation on

page 31.

concentric termination installation

1. Concentric terminations must be ordered separately.

SUF 100 120 - 250 models must use the 4 inch concentric

termination; Part Number: 9006328005. Contact your local

distributor or call the parts department phone number on the

back cover of this manual to order concentric terminations.

2. Determine the location for the termination.

note: roof termination is preferred since it is less susceptible

to damage, has reduced chances to intake contaminants and

vent vapors are less visible.

3. When installing a concentric termination vertically through the

roof; ensure that all exterior vertical clearance requirements

for the concentric termination, shown in Figure 30 on page

31 are being maintained. These clearances and those

cited by local and national codes must be maintained.

4. When installing a concentric termination vertically through a

flat roof, the termination's vent cap must be a minimum of 10

feet (3 m) away from any parapet, vertical wall or structure as

shown in Figure 28.

CONCENTRIC TERMINATION(S)

MUST BE A MINIMUM OF 10 FEET

(3 m) AWAY FROM ANY PARAPET,

VERTICAL WALL OR

STRUCTURE.

CONCENTRIC TERMINATION

FLAT ROOF CLEARANCE

figure 28