Barracuda 2LP Installation Guide, Rev. E

17

1

Measured with an average reading DC ammeter. Instanta-
neous +12V current peaks will exceed these values.

2

A

10% tolerance is permissible during initial start of the

spindle but must return to

±

5% before reaching 7,200 RPM.

The

±

5% must be maintained after the drive signifies that its

power-up sequence has been completed and that the drive
is able to accept selection by the host initiator.

3

See the

+

12V current profile in the

Barracuda 2LP Product

Manual (publication number 83328930).

4

This condition occurs when the Motor Start option is enabled
and the drive has not yet received a Start Motor command.

5

See “Conducted noise immunity” in the

Barracuda 2LP

Product Manual. The specified voltage tolerance is inclusive
of ripple, noise, and transient response.

6

At power-up, the motor current regulator limits the

+

12V

current to an average value of less than 1.4A, although
instantaneous peaks may exceed this value. These peaks
should measure 5 msec duration or less.

7

Minimum current loading for each supply voltage is not less
than 4% of the maximum operating current shown.

8

Use separate ground returns for

+

5 and

+

12V supplies.

9

Where power is provided to multiple drives from a common
supply, carefully consider individual-drive power require-
ments. Where multiple units are powered on simultaneously,
be sure the peak starting current is available to each device.

10

Operating condition is a third-stroke seek at OD and read
one Track. The command is issued every 0.075 seconds
(every 0.063 seconds on wide and SCA drives).