SERIES 28A BOILER INSTALLATION AND OPERATION INSTRUCTIONS

9.

Assemble the rest of the sections following steps 3
through 8 above.

10. Hydrostatically test the boiler by following the

instructions on page 8.

11. While the boiler is being filled confirm that all

of the draw rods are properly torqued and that
there are no leaks.

12. If any leaks are found tighten the draw rods on that

section until the leak stops.

Cleanout Cover Installation
1.

The cleanout covers come insulated from the
factory. Inspect the covers to ensure that the
insulation is not damaged or missing. If it is call the
Smith Customer Service Department.

2.

Trim the 1/2" rope that's sticking out around the
cleanout opening flush with the castings to insure
an air-tight seal, see Figure 5.

3.

Install the cleanout cover bolts from the inside of the
cleanout cover and start the nuts, Figure 7.

4.

Insert the cleanout cover and tighten the nuts to
15 ft lbs,

21 Nm.

5.

Apply a bead of high temperature silicone caulk
around the perimeter of the cleanout cover to
ensure an air tight seal.

Figure 7 - Cleanout Cover Assembly

Burner Mounting Plate Installation, Figure 8
1.

Apply two coats of the spray adhesive supplied with
the boiler to the rope groove on the plate. Allow time
for the first coat to dry then apply the second coat.
When the second coat is tacky lay the 3/8 rope into
the rope groove and press it into place.

2.

Screw the four 7/16-14 x 2 1/2" studs into the
tapped holes in the boiler front section, Figure 8.

3.

Install the burner mounting plate insulation block in
the burner opening in the front section of the boiler.
The small observation port cutout must be on the
top, left side.

4.

Align the four holes in the burner mounting plate
with the 7/16" studs and force the burner insulation
block inward until the studs extend far enough
through the burner mounting plate holes so the nuts
can be started. Lightly tighten the nuts.

5.

Carefully insert the 1/4-20 x 5" machine screws
through the holes in the burner mounting plate and
insulation block, Figure 8. Reach through the inside
of the burner opening and install the stainless steel
fender washers and nuts and snug the nuts down.

CAUTION: The burner insulation block must be
supported from the inside to prevent it from tearing.
Don't force the bolts through the block or over
tighten the nuts or the block with be damaged!