Inspection and Installation

14

3.2

Handling Unit on the Skid

Transport the unit using a fork lift or a crane with sling and spreader bars.

• If using a fork lift, make sure the forks (if adjustable) are spread to the widest allowable distance

to still fit under the skid.

• Ensure the fork length is suitable for the unit length.
• When moving the packaged unit, do not lift the unit any higher than 6" (152mm) off the ground.

Exercise great care if the unit must be lifted higher than 6" (152mm). Personnel not involved in

moving the unit must be at least 20' (6m) from the lift point of the unit.

3.3

Unpacking the Unit

Remove outer packaging when ready to install the unit. Be sure to locate, and set aside, the bag of

mounting hardware that is to be used for mounting the support legs on the unit.

Figure 12 Removing shipping crate

Three-fan unit shown for illustration.

Methods for other sizes of condensers are the same.