Mounting – Raritan Engineering toilet User Manual

Page 8

Advertising
background image

8

MOUNTING

A. Preparation for Mounting Toilet

Mounting surface must be flat and solid.

Seat must open more than 90 degrees.
1. Place the toilet and mark mounting holes’

center line, and outside of the bowl
(see FIG 1.) Draw a center line between two
holes. Mark front hole outside and center and
draw a line perpendicular to first center line.

2. Mark three lines A, B, and C, 3/8” from outside

lines.

3. Line up outside edges of the brackets with marked

lines A, B, and C.

4. Secure the bracket assembly to deck using #14

self threading bolts and flat washers.
Note: place bolts as close to mark lines A, B,and
C as possible

5. Drill holes for discharge (1 5/8” (41 mm.), inlet

hose (7/8” (22 mm.) and wires (3/4”(19 mm.) using
dimensions shown in Fig. 2.
Note: check outside diameter of the hoses and
adjust hole sizes accordingly.

6. Complete plumbing and wiring before installing

toilet

2 5/8”

2 1/4”

DISCHARGE HOSE
1 5/8” (41 mm.)

INLET HOSE
7/8”(22 mm.)

WIRES
3/4”(19mm)

2”

1 3/8”

Fig. 1

Line A

Line B

Line C

Fig. 2

To install the toilet:

A. Prepare mounting location
B. Install plumbing
C. Install controls and complete wiring
D. Connect hoses and wiring to toilet
E. Mount toilet

3/8”

Bolt and

washer